1. What was planned?
*Finish the first puzzle for Bunny Generals
*Work on the playground website

2. What was done?
*Finished the first puzzle for Bunny Generals
*No website updating will be done until he have a content management system, so I'm look into Joomla!

3. Problems encountered?
*Not really any problems with Bunny Generals it just takes time.
*Never worked with any sort of content management software for a website.

4. What did you learn this week?
*A little bit about Joomla! from some tutorials at joomla.org

5. What's planned for next week?
*Refine the Bunny Generals first puzzle to include lots of dialogue so the player will know exactly what to do without asking any questions, and add a console or hud where the player can review previous instructions and objectives.

6. Hours worked.
*About 14