1. What was planned?
*Implement the suggestions received from Dr. Barnes and everyone at the gamelab meeting.
*Link up with Katie at some point a create a preliminary GDD, and sitdown and get her up to speed on the code so she can work on it easily, (I probably should clean up the code).
2. What was done?
*Added most of suggestions to the code, still need to find better art that scales up well.
3. Problems encountered?
*Dr. Barnes and myself have conflicting schedules so having time to meet up is proving difficult.
*A GDD for Bunny Generals may have to wait for now, the end up the semester is bringing lots of work.
4. What did you learn this week?
*Using game library's and registering services in XNA( Ketih, and creators.xna.com)
5. What's planned for next week?
*Completely Finish This Bunny General sample(all positive feedback) and implement a logging system for when studies are done.
6. Hours worked.
*About 8 hours.