1. What was planned?
finished fixing problems with for loops
codebase clean up
visually enhanced dance tool
finish implementing xml schema
add survey to the dance tool
get timeline working
get durations implemented
2. What was done?
finished fixing problems with for loops
codebase clean up
visually enhanced dance tool
3. Problems encountered?
Class assignments flared up again...
4. What did you learn this week?
a clean codebase is a happy/ more understandable codebase
5. What's planned for next week?
make some more miracles happen via another code clean up
6. Hours worked.
Alot... lets see... i was here till 3am every day last week. i think that was an extra 30 hours than usual. prolly 70% of that was dance tool time.