Amanda's report 09/28-09/09 (two weeks)

1. What was planned for this week. Camera fixing, more level testing of the third level, began prep of the engine for RealityWorks. Hold office hours for the discrete math class for their test.

2. What was done. All of that plus the games repitches in the serious games class.

3. Problems encountered. The third level parsing is not working correctly. Have to fix that and the camera...

4. Plan for next week. Third level parsing, one click installation, camera.

5. How many hours worked. 24